<< Click to Display Table of Contents >>
Exercises |
1.Import the electrical model using the tool to import data objects. To do so, right-click the Power Configuration object and select the Electrical Model - Synchronize Data Objects option.
2.Leave selected the default option Synchronize all Data Objects from the Electric Model and click OK.
3.Leave selected the default option Create a new project for each new object and click OK to create a new project file for each Substation and Feeder registered in the model. Click OK to finish.