<< Click to Display Table of Contents >>
Including a Substation and a Feeder |
1.Insert in the electrical model the Substation SUB03 and Feeder FE03, according to the next figure.
Substation SUB03 and Feeder FE03
2.Model Substation SUB03 exactly as performed with Substations SUB01 and SUB02.
3.Model Feeder FE03 according to the next figure.
Feeder FE03
NOTE |
Terminals 1 must be placed facing the source. |
4.Update the Schematic Diagram of Operation according to the next figure.
Schematic Diagram of Operation
5.Update the model's copy to allow a simulation.
6.Configure the spreadsheet Device_List with the same philosophy of selecting an adjustment group, that is, Group 1 equal to normal flow status, Group 2 equal to feeding RL03 load, and Group 3 equal to reverse flow. Consider Reclosers RL04, RL05, and RL06 as belonging to Cooper_F6 model.
7.Create a spreadsheet for Substation SUB03.
8.Use parameters for load and current limits equal to all other devices.
9.Update the system and perform all triggering tests.