<< Click to Display Table of Contents >>
Configuring a Priority Load |
1.Insert in the electrical model of Feeder FE02, downstream of device RL03, a Distribution Transformer called "DT01" and configure the SelfHealingPriority property with value 1 (one).
Transformer DT01
2.Insert in the electrical model of Feeder FE03, downstream of device RL06, a Distribution Transformer called "DT02" and configure the SelfHealingPriority property with value 2 (two).
Transformer DT02
NOTE |
There is no need to insert these same objects in Feeders Simulate_FE02 and Simulate_FE03. |
3.Update the diagram SchematicOperation in the Electrical Modeler.
Diagram SchematicOperation
4.Update the operation Screen of Elipse Power.
5.Execute tests validating that priority is respected during recomposition.